schola guide rapport - valeur acquise
![]()
The Earned Value report displays, for each team, the graphs (or “S” curves) of their cumulative Planned Value (fixed in week 1), the Actual Cost and the Earned Value:
Example comments: Team#1 were, at week 20 only slightly over budget and behind schedule, but then the Actual Cost went further above the Planned Value in the final weeks.
Click on “CPI SPI Indices” to access this report